The model line is a value stream or a section of a value stream used as a pilot to demonstrate an organization’s capability to deploy lean systems and behaviors. The model line approach is used early in an organizations lean journey as a way to achieve rapid results in a focused area, learn about both lean and what it takes to implement, and to prepare for wide-scale lean implementation. A good test of a model line’s maturity is to ask one or more people with deep expertise in lean to conduct an audit. Two full days are recommended even for model line of limited scope, to allow for enough time for several gemba walks with management, informal interviews of support staff and people on the line, and the presentation of a summary of findings. If pressed for time, and wanting a quick guide to gauge the maturity of your model line, here are 21 questions you can start with:
1. For how many consecutive days was the required demand met within regular hours?
The answer may seem to be “the longer the better” but in fact a 100% rate of operation suggests plenty of slack or hidden problems. The target should be around 95%, or perhaps that one day in twenty required overtime. Taiichi Ohno taught us that the line that never stops is either really great or really bad. Whatever the answer to this question, it should yield hints of the areas of losses on the line and point to other areas of questioning.
2. What is the status of the production for the hour against plan?
One of the first things you see on the model line should be an “hour by hour” chart of hourly production control board. A digital version simply will not do. At an advanced stage it may be allowable, but when first implementing lean the manually updated white board or flip chart production control board insures local ownership and engagement. Be sure to check on the freshness of the information and that where problems have been identified, the team has thought through to the root causes.
3. How do teams on the model line begin their shift?
4. Where is the pacemaker process?
The pacemaker is more than a mechanical point for setting the speed or “pacing” the line, it is the single location where scheduling takes place. The remainder of the line should be triggered by the pull signal from the pacemaker. Too many model lines operate on quasi-pull due to lack of a clear pacemaker.
5. How are “islands” or processes set apart or isolated from the upstream and downstream processes connected?
A model line need not necessarily a series of equipment in a contained area or even a physical production line. The value stream may span several departments and be physically disconnected. While this is not ideal, rearrangement of equipment is not always a practical first step as part of a model line project. In fact the moving of equipment can become the end in itself, even taking resources away from training or improvement to the equipment in situ. It is better to ask how standard WIP, the pulley system (tsurube) and other methods are used to pull between islands.
6. Where are the standard work documents?
The standard work chart(s) should be visible. Hunting and retrieving standard work documents from their storage place is far from world class.
7. How well is standard work being followed?
This is a question rich in possibilities. Is the standard work easy to follow? Does it appear easy? Is it in fact easy? Why or why not? The better and more detailed the standard work, the more ways this question can enlighten us as to the maturity of the model line.
8. Does standard work exist for occasional work such as tool changes, material changes and the replacement of empty or full containers?
Many times problems are hidden in the occasional or filler work. When this work is timed and standardized it becomes possible to improve it. Another way to ask this question is, “What has not been standardized and why?” This one is a lot of fun, but can put the questioned in an awkward spot. It should be used only when there is enough trust and rapport with those people.
9. When was standard work last updated (improved)?
The smaller this number the better, as long as the unit is never more than days. Twenty one is a good initial target for a mature, stable model line.
10. What percentage of balance to takt time has been achieved for manual cycle times for individual stations?
The model line should display a yamazumi chart that shows stacks, like wooden blocks, the individual work elements at each station. Against a horizontal red line of takt time, some stacks will be naturally taller than others unless perfect balance has been achieved. An overall balance to takt time of 95% is ideal but for mixed model production 10%-15% is common. Also look for kaizen activities generated from imbalances on the yamazumi.